Click on a  photo to see more photos of that week's activity.

<--------------
Previous page

Construction Chronology - page 4

             
                               Week of October 3, 2009

 

One of the Bathrooms and the kitchen cabinets were primed. One of the main rooms got a second coat of primer. Jean continuesdscraping floor tiles in the pastor's office. The outside got most of the attention this week with 4 guys working out there.

                
                                 Week of October 10, 2009

 

The outside roof project git more attention. The tree trimming and cleanup moved to the front side yard. All the tiles were removed from  the Pastor's office floor. Priming, priming, priming.


                               Week of October 17, 2009
 

Rain is the key word here. We discovered many more leaks from the roof and in through the doors. We unloaded a stove and put it into position. Jean began painting the floor in the Pastor's office. And there's a new broom cupboard.



                                   Week of October 24, 2009
 

A combination heater and A/C unit was installed in the office. Mark removed floor tiles in the bathroom. A false wall in the rear room was opened to reveal a closet with a hole in the floor into the crawl space. The rear wall got prepped for primer. The cabinet doors were installed on the wall behind the stove.