                               Week of October 31, 2009

Another rainy day. A Japanese Maple tree was moved and some paving was put down. Rich put on rain gear and cleaned mud off the new parking lot. Old pipes were removed from holes in the floor. Don built an access hatch. The closet holding the hot water heater was opened up. The hot water heater is tested. The room heater got some trim.

                
                                 Week of November 7, 2009

 

Bruce and Bob searched for the leak in the roof and found a likely candidate. Lots of priming went on in the back rooms. The hot water heater and an old doorway was removed.  The furnace was turned on. Tape was scraped off walls.


                               Week of November 14, 2009
 

The back bathroom got stripped of fixtures and cabinets, then primed. The blocks in the Pastor's office were cleaned and made ready for prrimer. The red room, back bathroom, and Pastor's bathroom all got primed. Some of the rubber mulch and much of the rubble were dumped into the dumpster.



                                   Week of November 21, 2009
 

The shower stall and interior walls were removed from the back bathroom. The colorful blocks in the Pastor's office were primed. The bobcat returned (again!) to clear the backyard.


***** 2009 construction ends! *****